How Long Do Custom Pins, Coins and Medals Take? A Realistic 4 to 8 Week Timeline
The timeline step by step
After the mold fee is paid we send a proof for you to confirm; some customers confirm the same day, others take several days. The physical sample then takes about 7 days. Once you approve the sample and pay the 50% deposit, mass production starts. It takes 10 to 15 days normally and around 20 days in peak season; we are busy all year, so plan for about 15 to 20 days. Then shipping. Plan about 4 to 8 weeks in total.
| Step | What happens | Typical time | Who controls it |
|---|---|---|---|
| Quote | You send artwork, size, quantity, destination and your date | We reply within 24 hours | Us |
| Mold fee | Paid first through PayPal; this starts the order | n/a | You |
| Proof | We send the proof (artwork) for you to confirm | Sent after the mold fee is paid | Us |
| Proof confirmation | You confirm the proof | Some customers the same day, others several days | You |
| Physical sample | We make the physical sample | About 7 days | Us |
| Sample approval and deposit | You approve the sample and pay the 50% deposit | Your decision | You |
| Mass production | Production starts after approval and deposit | 10 to 15 days normally; around 20 days in peak season (plan for about 15 to 20) | Us |
| Shipping | The balance is paid before shipment | Depends on method and route, quoted separately; air freight typically 4 to 7 days in transit | Carrier |
| Total | Mold fee to delivery | About 4 to 8 weeks | n/a |
Which steps you control and which we control
You control how fast you confirm the proof, how many people need to approve it, and how fast you approve the physical sample. We control the sample (about 7 days) and mass production (10 to 15 days normally and around 20 days in peak season; plan for about 15 to 20). The quickest way to save time is to name one person who approves the proof and the sample, and to send complete details with the first quote request.
Why this is 4 to 8 weeks and not 2 to 4
Some suppliers quote production time alone, or start counting after the sample is approved. Our 4 to 8 weeks starts when the mold fee is paid and includes proof confirmation, the physical sample, production and shipping. Tip: ask any supplier which steps their number includes.
What can make it longer
- Slow proof confirmation, or several people who must approve the proof or the sample.
- Sample revisions.
- Peak-season production: around 20 days instead of 10 to 15. We are busy all year, so plan for about 15 to 20 days of production.
- Complex designs.
- Quantity, destination, carrier capacity and customs, which depend on the order and the route.
Counting back from the date you need it
Work back from the day the items must be in your hands, not the event date itself, and allow time to receive and check them. Plan for the 8-week end of the range. If your date is closer than that, send it with the quote request and we check the schedule against your actual project before confirming.
| Start from | Subtract | Result |
|---|---|---|
| Your in-hands date | 8 weeks | Latest day to pay the mold fee and send the artwork |
Rush orders can ship in as little as about 7 days in the best case, depending on design and quantity. Rush production is available for an added fee, so you get your order faster. See rush orders for events.
Shipping time is separate
The 4 to 8 weeks runs to delivery, so it includes shipping. Courier and sea freight take different times and are quoted per route. Air freight typically takes 4 to 7 days in transit. That is transit time only, not a delivery promise. Freight is listed as a separate line in the quote, and DDP depends on the destination and order. See shipping and duties for custom coins, pins and medals.
What to send for a schedule check
- Artwork or sketch.
- Size.
- Quantity per design and color. Standard MOQ 50 pieces per design and color; smaller batches negotiable depending on the actual situation.
- Plating and colors.
- Packaging.
- Destination country and city.
- Your real in-hands date.
- Who approves the proof and the sample.
One real order timeline
For one real order of 400 plated medals with lanyards for an association's annual event in Spain, the time from proof confirmation to delivery was about one month in total. The design drawing took about 1 week, the physical sample was ready on day 10, production took about 2 weeks and shipping about 1 week. This was one order, not a typical time and not a promise; our general plan stays about 4 to 8 weeks from the mold fee to delivery. Read the full case on our order-process page.
Frequently asked questions
How long do custom enamel pins take to make?
Plan about 4 to 8 weeks in total. After the mold fee is paid we send a proof for you to confirm, and the physical sample then takes about 7 days. Once you approve the sample and pay the 50% deposit, mass production takes 10 to 15 days normally and around 20 days in peak season (plan for about 15 to 20 days), then shipping.
How long do custom challenge coins take?
The same steps and total apply as for pins: proof, physical sample (about 7 days), mass production (10 to 15 days normally and around 20 days in peak season; plan for about 15 to 20 days), then shipping. Plan about 4 to 8 weeks from the mold fee to delivery.
How long does the physical sample take?
About 7 days after you confirm the proof.
How long does mass production take?
Mass production takes 10 to 15 days normally and around 20 days in peak season. We are busy all year, so plan for about 15 to 20 days. Production starts after you approve the sample and pay the 50% deposit.
Does the 4 to 8 weeks include shipping?
Yes. The total runs from the mold fee to delivery, so it includes shipping. Freight is listed as a separate cost in the quote, and transit time depends on the method and route.
Why do some suppliers say 2 to 4 weeks?
Some suppliers quote production time alone, or start counting after sample approval. Our 4 to 8 weeks starts when the mold fee is paid and includes proof confirmation, the physical sample, production and shipping. Ask any supplier which steps their number includes.
What can delay my order?
Slow or multiple approvers on the proof or the sample, sample revisions, peak-season production (around 20 days instead of 10 to 15) and complex designs. Quantity, destination, carrier capacity and customs also depend on the order and route.
When should I order for a fixed date?
Work back from the date the items must be in your hands, not the event date, and plan for the 8-week end of the range. If your date is closer, send it with the quote request and we check the schedule against your project before confirming.
How fast do you reply to a quote request?
Within 24 hours, with the pieces, the mold fee and shipping as separate lines.
Who controls the proof time?
You do. We send the proof after the mold fee is paid and you confirm it; some customers confirm the same day, others take several days.
Can you rush an order?
Yes. Rush orders can ship in as little as about 7 days in the best case, depending on design and quantity. Rush production is available for an added fee, so you get your order faster. See rush orders for events.
How long does air freight take?
Air freight typically takes 4 to 7 days in transit. That is transit time only. Freight is a separate cost in the quote, and DDP depends on the destination and order.
Does the factory have a peak season?
We are busy all year, so plan for about 15 to 20 days of production (around 20 days is typical).
Do you have a real example of how long an order took?
Yes, one order: 400 plated medals with lanyards for an association's annual event in Spain took about one month in total from proof confirmation to delivery. It is one order, not a typical time or a promise; the general plan is about 4 to 8 weeks from the mold fee. See the case on our order-process page.
Get a schedule check
Send your artwork, quantity, destination and real in-hands date. We reply within 24 hours and check the schedule before confirming.